on 12-21-2006 9:24 AM
Hi guys,
i am new with the topic "Quality Management". If I want to assign the items of the Testing schedule a inspection plan i get the error message: "The inspection plan entered is not compatible with the strategy " QST078. In the description of this message i read the advise to assign the inspection plan the same strategy as i had assigned to the testing schedule which is also a maintenance plan. But the problem is a searched every tab and mask in my inspection plan with transaction QP02 but i did not find any function for assigning the strategy to the inspeciton plan or a package of the strategy to any operations of the inspection plan. I searched also help.sap.com but I only found there a note that the assignment of packages to the operation is possible and necessary for the stability study but i did not found any guide for this. So if anyone can help me i would appreciate this.
Thanks for your help guys.
BR,
Bernd
Hi
what is usage of inspection created for stability study? I dont have system here to test it. please check and change inspection plan usage in header and try.
regads
Srinivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srinivas,
thanks for your answer. First we had inspection usage 5 (goods receipt) now we tried with usage 4 (plant maintenance) and 9 (material inspection) but we did not find any field for inspection strategy or its packages in the header nor the actions of the inspection plan. Perhaps you know any way of solution.
BR,
Bernd
KBA created in the topic:
3239483 - QST078: The inspection plan entered is not compatible with the strategy (stability study)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.