We currently have a test environment which consist of ECC5, TREX and KPRO.

Reason for this message is that we have been asked to refresh the ECC5 system from a copy of production (remaining SID) and have some concerns over the impact on the links between the components.

Anyone had exposure to such a scenario. We believe that the best option is to refresh all three environments

regards

Alan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Allan,

Sytsem copy will change all the settings that enable interaction between ECC,TREX and KPRO.

You need to restore all these as part of post system copy activities. BDLS will restore a lot of these. Some specific settings need to be manually restored.

Please award points for useful info.