Planned order in MD04

Former Member
0 Kudos

Dear PP Gurus,

We had an urgent problem when we executed MPS. In MD04 for the

materials the stock goes under zero. Because MRP created dependent

requirement in a past date and its quantity is very high (with one

item). In normal case it must have created for present or future dates

in many items. So the requirement amounts could be lower quantities and

right dates. The reason for this "one requirement in past date" is

a planned order as you know. Planned order is also on the wrong date.

But the independent requirement dates these cause the corresponding planned order are in many items and disributed along 2007 year.

Can you please help us?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thank you for your cooperation Mr Schulz.

It did work.

Best regards,

Evren Temiz

former_member583456
Active Participant
0 Kudos

Hi,

choosing an appropriate lot size procedure will create many small planned orders instead of one big planned order, see transaction OMI4.

Best regards

Thomas