on 04-25-2017 7:49 PM
Hello,
I need some help for automatic shift proposal in confirmation for Night shifts.
Following settings are made in OP4A (Shift Definitions):
Group: 02 Desc: Shift Sequence
No data for work break schedules since it is expected to run 24 hours a day.
Shift Definitions:
1 Morning_Shift 01.01.0001 31.12.9999 06:00:00 13:59:59
2 Evening_Shift 01.01.0001 31.12.9999 14:00:00 21:59:59
3 Night_Shift 01.01.0001 31.12.9999 22:00:00 05:59:59
No Overlap in shift timings. Shifts starts from Morning 06:00 to Next day 05:59.
Shift Sequences:
PP 1 Production 1 1 1 1 1 1 1
PP 1 Production 2 2 2 2 2 2 2
PP 1 Production 3 3 3 3 3 3 3.
This group is assigned to the workcenter.
Also, in Confirmation parameters and Single screen entry definition (OPK4 and OPK0), parameters are maintained.
I am getting correct data for Morning and Evening shifts. that is, shift is automatically proposed during the confirmations in Morning and Evening Shifts.
Issue is with the Night shift only. Night shift is not proposed automatically.
Is it because it goes across the days? or is there any other setting for night shifts?
Pl guide how to resolve this error.
Thanks,
Dheeraj
Hi Dheeraj,
In my opinion it is not possible, but what setting you have done in OPK0, default tab shifts.
Let other group members have their views
regards,
Solomon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Folks, help pl
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Any suggestions/answers?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.