Skip to Content

The changes in MM02 are not creating the log

Hi!

The changes in MM02 are not creating the log when I change in the MRP 1 vision.

The data are not saved in the CDPOS & CDHDR tables.

Does anybody kown how i can solve this problem?

Thanks!

Clayton Barbos

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Apr 27, 2017 at 12:33 PM

    manual changes will create change documents which can be found in the change history im MM03 > environment menu

    Or alternatively in transaction MM04

    About what specific field are you talking?

    Maybe there is a known issue in SAP Notes

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 25, 2017 at 08:23 PM

    What does this transaction do? I do not have this transaction at all in my system. Is there eventually a typo in the subject and the content?

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 26, 2017 at 06:53 AM

    Hi Clayton,

    Please explain little more, because the table you gave in your question having different data, transaction code ME02 is not available in the system.

    And what does it mean MRP1 Vision; are you talking about MRP1 view of material master record?

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 27, 2017 at 12:11 PM

    Hi!

    The transaction is MM02.

    I want to konw if it has a config to the "change document for material".

    The MRP 1 is view.

    When I change some information in it, this change is not in the "Display changes".

    Thank you.

    Add comment
    10|10000 characters needed characters exceeded