Hi Team,

I am configuring MRP for re-order point planning.

As per the requirement, we do not want to implement the MRP at MRP area level but on plant level. Hence in the config node "Activate MRP for MRP area ", the checkbox is not ticked at client level.

However the report RMDBVM00 was executed by mistake. Hence the planning file entries at plant level are converted into MRP area level. (Entries from table MDVM deleted and DBVM updated)

Now when we are running MRP using tcode MD03 or MD02 we are getting error message like "Plant does not exist"

Can someone please assist in analyzing the cause of the issue and the possible resolution.

Regards,

Mitesh Shah