Is it possible to change "actual finish date", when order is already closed?

Former Member
0 Kudos

Dear Gurus, please help me.

Our Production department forgot close in SAP timely all finished production orders, were produced 21/4/2017. Today is 25/4/2017 and all PO´s was closed today, SAP generated "actual finish date" like 25/4/2017. Exist any possible pocedure, how to change the "actual finish date" from 25/4/2017 to 21/4/2017? If not, can we change manually "actual finish date" before closing in CO15?

Thank you a lot

Accepted Solutions (0)

Answers (3)

Answers (3)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Did you try to post a new confirmation with the deired date?

former_member424010
Participant
0 Kudos

if you mean the actual finish date on the Date/Qties Field of the process order, that date is updated by the system using the posting date on the goods receipt. That date defaults the to current date when the GR is processed and while most people just accept the default date but can be changed before posting. Once the GR is posted and the field is updated the only way to change it would be to reverse the original goods receipt and reprocess it with a different posting date..

jessica_li
Advisor
Advisor
0 Kudos

Hi Tomas,

Which date do you mean by "Actual finish date"? Can you share a screenshot?
Anyway, I don't think the date set by confirmation or delivery can be manually changed in standard.
best regards,
Jessica