cancel
Showing results for 
Search instead for 
Did you mean: 

Default Operations In Work Order

0 Kudos

Hi,

I have scheduled about 100 single cycle maintenance plans via running a batch job & program RISTRA20.

However the batch job ran successfully and order created in the system. By default when order gets generated via scheduling of the plan, only 1 line item (0010) comes in operations tab of the order but in my case 2 line items (0010 & 0020) are coming by default in order which gets generated via maintenance plan with same description.

Please let me know why its coming twice, it should be only 1 time by default

Accepted Solutions (0)

Answers (2)

Answers (2)

peter_atkin
Active Contributor
0 Kudos

https://launchpad.support.sap.com

But you will need a logon ID.

PeteA

Its ok Pete. I resolved it, I untick the notification check box in SPRO - Define notification and order integration settings.

peter_atkin
Active Contributor
0 Kudos

Nimish,

Are you using and plan/order developments? If so, then deactivate them and retest.

I also remember seeing an old OSS Note with a similr issue - so have a look on OSS too.

PeteA

0 Kudos

Hi Peter,

No I am not using plan/order developments. Can you please share the link of the OSS