Hello Experts,

In the Option Profile in CM01, SAP already provide a profile SAPB023 for 78 weeks. However even when I schedule production orders in 13 months for example, the profile SAPB023 in CM01 displays capacity requirement till week 42 only.

Is there anything specific that must be done so that the report display orders till week 78.

Thanks.

Regards,

Nazim