Skip to Content
0

PE set date in MF50

Apr 25, 2017 at 09:01 AM

39

avatar image
Former Member

Hello ,

when I'm setting the PE in MF50 I want start date to be Monday and finish date Friday.

at this moment in MD04 start date is random ( I don't know why ) and finish date also ...maybe start date is when the PE was created ...its possible

there must be a setting where I can do this

please help me :)

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
May 02, 2017 at 06:23 PM
0

Hello

Your dates are probably being calculated by lead-time scheduling. I suggest you to read carefully the following notes to understand the behavior of transaction MF50:

178525 MF50: Explanation --> scheduling as of Release 4.0

165280 MF50: Not possible to change to production dates

Regards,

Caetano

Share
10 |10000 characters needed characters left characters exceeded