when I'm setting the PE in MF50 I want start date to be Monday and finish date Friday.

at this moment in MD04 start date is random ( I don't know why ) and finish date also ...maybe start date is when the PE was created ...its possible

there must be a setting where I can do this

please help me :)

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 02, 2017 at 06:23 PM

    Hello

    Your dates are probably being calculated by lead-time scheduling. I suggest you to read carefully the following notes to understand the behavior of transaction MF50:

    178525 MF50: Explanation --> scheduling as of Release 4.0

    165280 MF50: Not possible to change to production dates

    Regards,

    Caetano