Hi there

In SolMan 4.0 SP6

If a change request (in fact the change document) is assigned to a maintenance cycle and no transport request is created yet for the change, is there any possibility to switch the link of the change document to another maintenance cycle? and similar:

If a change request (in fact the change document) is assigned to a maintenance cycle and transport requests are already created yet for the change, is there any possibility to still switch the link of the change document to another maintenance cycle?

if not, what do we have to do if mistakes have been made? or does a workaround exist?

regards

Steven