Afternoon,

I am looking at ways that i can supply components to a customer whom in turn is going to use them in an assembly but deliver the assembly to another site

We have a purchase order in place for the finished assemblies. In order for us to deliver the components that are to be consumed can we use the SUBCONTRACTING procedure?

Setting it up as Q & L with the Assembly Material number and then having the components listed.

When i do go to action this the assembly already has a BOM but is calling up different parts. I want to supply from plant 2000 but want the assembly to be delivered to plant 1000. looking at the other components these are all marked plant 1000 & storage 1000.