Change period interval on capacity planning board from weeks to days (CM25)

Hi Gurus,

In my case, order span is in hours. Therefore, I would like to schedule multiple orders in a day. To achieve this, I need to see the time scale on planning table (CM25) in days. Is it possible? Please share if any document to achieve this.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Apr 20, 2017 at 01:19 PM

    Hello Amit,

    Check the overall profile you are selecting in CM25. Next check the period profile maintained in that overall profile in below config path.

    Overall profile path -

    SPRO-->Production --> Capacity requirements planning --> Capacity leveling and extended evaluation--> Define overall profile

    Period Profile path -

    SPRO-->Production --> Capacity requirements planning --> Capacity leveling and extended evaluation--> Define period profile

    Here you can adjust the period as per your requirement. Else you can select the relevant overall profile to match your requirement.

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 25, 2017 at 05:59 AM

    Hi Raghava,

    Thanks for your response.I tried using overall profile SAPPI_G001, within which I used control profile SAP___C004 and period profile

    SAP___P002. This combination is required to get the desired outcome. However, after doing these settings, when I run transaction CM25, system does not take me to the capacity levelling screen. It remains on the initial screen only. Could you please advise further if I am doing anything wrong?

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 25, 2017 at 08:34 AM

    hi Amit,

    copy the overall profile SAPPI_G001 and create custom profile . And Add period profile with 24 splits and see the results.

    regards,

    Solomon

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 26, 2017 at 04:42 AM

    Hi Macwan,

    I changed time scale profile to SAP___M021 within planning tab profile and it worked.

    Thanks for your inputs :)