Dear Gurus,

I have already setup the tables for 2LIS_03_BX and 2LIS_03_BF, uploaded them in the cube 0IC_C03 and compressed suitably.

For filling the setup table for 2LIS_03_UM, when I execute OLIZBW, company code is mandatory. As I have 6 companies, I gave * for company code but no records get picked up.

If I decide to do 2LIS_03_UM setup 6 times for 6 companies, do I have to make the table MC03UM0SETUP blank 6 times? Do I have to do INITupload in the cube 6 times and then DELTA also 6 times?

If I do "deletion of setup data" (Tx LBWG) 6 times, will it have any side effect on the 2LIS_03_BX and 2LIS_03_BF which have already been setup and uploaded in the cube.

Kindly advise.

Regards

Lalit Kumar Jain

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Iam filling the setup tables for 2LIS_03_UM for one company code. And when iam checking the setup tables after that ,iam not able to find any rows in it.

I checked RSA3 also. No data...Please suggest what to do.

I have already loaded 2LIS_03_BX and 2LIS_03_BF into cube and compressed them as per the setting required.Now iam trying to load 2LIS_03_UM also..

Former Member
0 Kudos

Run the setup tables for 6 times with different company codes and then do the init/delta.

Former Member
0 Kudos

Hi,

And you can also fill the setup table for all 6 Company codes at a time , if your R/3 has Sufficient resources.

With rgds,

Anil Kumar Sharma .P

Former Member
0 Kudos

Hi Anil

Could tell me what resources do you need in R/3 to fill up all the setup tables at a time.

Former Member
0 Kudos

You can simply run one init and one delta fro UM after 6 setup run.

Hope it helps.

Regards

Former Member
0 Kudos

You dont have to delete all the time, it just a selection. After doing statistical setup for 6 times. you setup tables will have records for all the company codes. You can do init later also