How to schedule multiple maintenance plans via IP30

0 Kudos

I have uploaded 300 Single cycle maintenance plans via LSMW. now I want to schedule all the plans by running a batch job and IP30. Please let me know the process of scheduling plans via IP30

Accepted Solutions (0)

Answers (2)

Answers (2)

sebastian_lenartowicz
Active Contributor

Greetings Nimish,

If you had specified the Start Dates for your plans, you should be able to execute IP30 deadline monitoring and generate planned Orders from your schedule (dependent on your Scheduling Parameters)

If you did not specify the start dates, you will need to do so in IP10 in order to start a schedule, then you can use deadline monitoring.

Follow the link from Maria Terence above to learn more about scheduling deadline monitoring as a batch job.

MTerence
Active Contributor
0 Kudos

Hi,

Refer below link

IP30 Setup

Regards

Terence