Hi,

I am trying to Transfer the budget values from PPM to SAP PS on L1 WBSE which is linked to the PPM item

I have Specified a financial view for budget transfer or planned cost transfer, and have selected the a CO version for this view in Customizing for SAP Portfolio and Project Management under Start of the navigation path Portfolio Management Next navigation step Global Customizing Next navigation step Portfolio-Independent Settings Next navigation step Define Financial and Capacity Views End of the navigation path.

I have mentioned Amount type of Transfer as Budget Transfer and Version as 0.

When pressing the button " Transfer to ERP" a popup appears and when I try to transfer, nothing happens.

I also tried automatic transfer via /RPM/CO_DOWNLOAD. But no result. Blank messages appear in the log

Can someone please help and let me know what I am missing here?

Thanks

AU

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 21, 2017 at 07:08 AM

    Dear Au,

    You can find information under the following Wiki-page:

    https://wiki.scn.sap.com/wiki/pages/viewpage.action?pageId=451055506

    Best regards,

    Judith

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 19, 2017 at 07:30 AM

    After doing the transfer, run the report

    /RPM/FICO_INT_PLANNING.

    Maintain the destination system where you have PS/WBS. It can be same as Portfolio Item

    Sumati