Hi All,
I have set job control for LO Extraction with 1 hour duration in R/3. All the jobs are showing Cancelled. The job is cancelling with Message Type X.
When I check the Short Dump, I got the following information.
<b>"Structures have changed (sy-subrc=2). You are using the 'Queued Delta' update method. You cannot use report RMBWV3nn (nn = the number of the relevant application in the logistics cockpit) to transfer an entry from extraction queue
MCEXnn to the corresponding delta queue because one of the
structures that is being used has been changed since the document
was posted. " </b>
How to resolve this issue,