on 12-02-2006 5:24 AM
Hi all,
Can anyone explain me about Pegging concepts in SCM, since i am new to SCM.
Thanks in advance.
Regards,
a.fahrudeen
Procedure in Production Planning and Detailed Scheduling that establishes the relationship between receipt elements and requirements elements of a product within a location. Using pegging, the corresponding receipt elements are assigned to the requirements.
Two types of pegging are available:
Fixed pegging
With fixed pegging the assignment of a receipt element to a requirements element remains fixed during planning.
Dynamic pegging
With dynamic pegging the assignment of receipt elements to requirements elements can change depending on the planning situation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi fahrudeen,
If you implement the component Grouping, Pegging, Distribution for project-based production procedures, you can use pegging to determine the proportional assignments of replenishment elements (production orders, purchase orders) for a grouping WBS element to the objects causing the requirements (reservations, planned independent requirements). These assignments form the basis for the cost distribution that follows and that distributes the costs for the procurement elements of grouped requirements to the original projects.
Pegging can be performed in two different ways:
When you make assignments according to MRP Logic, the assignment of replenishment elements to pegged requirements takes place according to the current requirements planning situation. Previous assignments are not taken into account.
The second option is the use of the Fixing Rule: during the assignment process, the attempt is made to copy as many assignments for a replenishment element as possible form the previous pegged requirements run. This means that cost transfer postings at a later date can be avoided.
Special rules must be applied for the assignment of exceptions (surplus, scrap and stock differences).
Prerequisites
To execute pegging, the following prerequisites must be met:
Grouped material requirements under one or several grouping WBS elements must exist for the WBS elements
You have assigned a distribution profile to your grouping WBS element in Customizing
You have assigned a logic for the execution of pegging on plant level in Customizing under Pegging: General Settings.
You have assigned rules for the assignment of exceptions in Customizing under Pegging: General Settings.
You have maintained the movement types that are allowed for pegging in Customizing.
You can find further information on the necessary Customizing activities in the SAP IMG under Logistics ® Project System ® Costs ® Automatic and Periodic Allocations ® Pegging and Distribution.
If you want to use a cost structure that deviates form the production structure, you have created break points.
You have created special WBS elements for the assignment of exceptions (scrap. surplus and stock differences) either on plant level or grouping WBS element level. You can find further information under Assigning Exceptions.
You have assigned grouping WBS elements of category 1 (valid for all materials) to a plant. You can find further information under Assigning Grouping WBS Elements to a Plant.
You have executed material requirements planning (MRP). You can find further information under Starting a Multi-Level Single-Item Planning Run.
Features
Pegging contains the following functions:
Determination of the pegged requirements assignments
Determination of break points
Assignment of exceptions (scrap, surplus, stock differences)
Processing assignments
Transfer posting material to material
Reporting
The following functions are not supported in pegging:
cross-plant processes
use of serialized materials
use of manufacturer part numbers or supersession materials
assignment of requirements form sales orders to projects
Transaction Codes/BAdIs for Pegging
Customizing Transactions
Transaction
Description
0PEG01
General settings
0PEG02
Maintain movement/transaction types
0DIS01
Maintain distribution profile
You can find the appropriate Customizing activities under Project System > Costs >Automatic and Periodic Allocations > Pegging and Distribution
Application Transactions
Transaction
Description
PEG01
Collective processing - pegging
PEG02
Manual maintenance of assignments
PEG03
Maintenance of break points
PEG04
Distribution of exceptions
PEG09
Assignment of grouping WBS element to plant
PEG05
Report: assignment overview
PEG06
Report: quantity structure
PEG07
Report: stock overview
PEG08
Report: display change documents
PEG10
Reconciliation report: compare stock
If it helps,please reward the point.
Regards,
Hareesha k
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.