Transfer Profile

Former Member
0 Kudos

Hi Everyone,

While I was creating activity for transfer profile it gives error saying 'Transfer to R/3 using mixed periodicities is not allowed'. And I am using 9ADP as periodicity. Now I changed the time bucket profile to accomodate days in it.

After doing that interactive planning gives error " read and write profile not match ".

My intention is to transfer data from APO to R/3.

Can anybody help me with that.

Thanks

John.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi John,

I guess I am giving you the answer very late and the problem might have already been solved. However try the following if the problem is not yet resolved.

The time bucket profile should have only one periodicity. Select Months in the Time bucket profile and schedule the transfer job again.

and it is always better to have only one keyfigure in the data view whose values you want to transfer, mostly Final Forecast. (Best Practise).

Best Regards

Raghu Kishore