Hi All,

I am facing a problem with delta extraction from 0HR_PT_2 datasource.

I am pulling delta data from R/3 daily and it is working fine, except in a case when a person create an open ended (end date = 31.12.9999) absence, for the past date, the extractor does not provide the data from the start date of absence but the current date. For Example:

My <b>last delta load</b> run was yesterday say <b>29.11.2006</b>.

The user creates the absence record with <b>Start Date = 25.11.2006 and End Date = 31.12.9999</b>.

While pulling the delta data, the extractor provides the data from the current date i.e. 30.11.2006. All the data from start date 25.11.2006 to 29.11.2006 is missed.

I have already defined the Time frame for Transfer and Reporting Time Types in R/3 system.

Does any body have faced the similar issue?

Thanks & Regards,

Ankit