There are 4 operation in our production order scenario inspection type (03) we wants the inspection lot to be created for 3rd operation what special setting needs to be done ?

Br, Kiran

former_member42743
Active Contributor
0 Kudos

Have you read the basic rules for this site? That is a farily standard, basic question an probably has multiple related questions on the web about it. Not to mention the SAP help files.

Please do some research, test and get back to us if you have a specific question.

Thanks,

Moderator

Accepted Solutions (1)

Accepted Solutions (1)

former_member409780
Discoverer

Hi Kiran.,

The lot is generated for result recording,UD etc, hence create an operation view with control key PP04 in routing CA01 and assign the relevant inspection characteristics to it and save the routing process. Record the results for the operation(3rd operation which you said ) defined in routing plan for the inspection lot generated and complete the UD.

Thanks in advance.

Kindly revert your feedback if useful.

former_member267531
Participant
0 Kudos

Thanks Kumar

We tried the above steps and now the inspection lot get created automatically.

Br, Kiran