Hi Expert ,

We have two Mfg plant . Planning plant is KX01 and supplying plant KX02.

1.In planning plant KX01 , we will execute MRP of FERT material .

2. Planned order against PIR will be generated in KX01 Plant.

3.Against planned order, Dep Req of component material will be generated in KX01Plant ( say 100 pc)

4.PR generated against Dep Req in KX01 Plant (say 100 pc)

5. Same PR will be generated in KX02 plant in separate storage location. ( say 100 pc in BG01 storage location ).

6. PR in KX01 will be converted to STO against KX02

7. PR in KX02 will be converted PO against external Vendor

8. Vendor will supply material to KX02

9.KX01 will procure material from KX02 against STO.

Please guide how I make configuration.

Regards

Amit Biswas

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Solomon Macwan Apr 18, 2017 at 11:23 AM
0

Hi Amit,

You can easily map the above scenario by special procurement

please see following link

https://archive.sap.com/discussions/thread/3160362

regards,

Solomon

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Solomon ,


Thanks for immediate reply ,


If you see point no 5 in my threat, where I mentioned PR in the supply plant KX02, will have to generate in separate storage location . [Ref : 5.Same PR will be generated in KX02 plant in separate storage location. ( say 100 pc in BG01 storage location ).]

As per your guideline every thing is happening except , PR is not generating in separate storage location as mention , it should be created in storage location BG01.

Please help , how to resolve the issue .

Regards,

Amit Biswas