on 04-18-2017 9:06 AM
Hi Experts,
I have checked the threads, but don't find relevant answer for the above error message. While executed the CKMSTART - Set valuation area as productive occurred the following error message:
Message no. MLCCS003
No cost component structure was found in valuation 1 for period 001 / 2017 in plant BAD1.
Appreciated your soonest message
Thanks & Regards,
Bhoom
Dear Bhoom,
Check SAP note 2342258 - Error MLCCS003 after MLCCS_STARTUP
Regards
Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check SAP Note also 206629 - Cost component structure not found for actual CCS.
Actual
costing uses the same cost component structure which is used in Product
Cost Planning as well.This ensures that the standard price used for
preliminary valuation and the periodic unit price calculated at the
period-end can be compared to each other cost component by cost
component.So as to enforce this, no separate setting option for actual
costing is available in Customizing.
The system searches for the cost component structure to be used as follows:
However,
if the above procedure (search via allowance for marking) could not
determine a valuation variant, the system finally checks whether it is
always the same cost component structure which has been defined for each
costing variant for the standard cost estimate in Customizing.If this
is the case, this cost component structure is of course used.
5. If the problem continues to exist, contact Development Support at SAP.
Kind Regards,
Can K'
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.