Hi,
I am wokring in cprojects. I have done the following entries
<u><b>cost revenue rate - defined</b></u>
amount costs - 50 US dollars /Hrs
amount revenue 10 US dollars/Hrs
different revenue - 1.0 US dollars / Hrs.
<b><u>resource assigned and staffed for 20 hrs</u></b>
<u><b>After calculate costs the value shown are</b></u>
proj defn -
20 hrs----
costs 89.80 USD
projet role -
20 hrs -
costs 39.80 USD
responsilbe person - 20hrs - costs 39.80 USD
Can anyone please explain me how this calculation takes place in cprojects 3.1.
Please do the needful
Regards,
Amit