Is it possible to carryout Loading onto a TU after Goods Issue has been posted for the assigned deliveries?

If so, is it possible by Configuration? Please let me know.

Standard SAP will not allow loading after PGI.

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Tom,

May I know why you want to load after PGI , any reason ?

0 Kudos

Hi Tom,

I am unable to know what is the exact requirement but system will allow loading into TU after goods issue too.

Step1: Create a delivery & Assign it to TU As below.

Step2: Complete Picking + Do Goods Issue.

So the system is throwing error so go to /SCWM/TU then do arrival at check point.

Now go back to Delivery & Do the Goods Issue.

Now Go to /SCWM/TU

Perform Loading + Departure from check point.