Loading after PGI

Is it possible to carryout Loading onto a TU after Goods Issue has been posted for the assigned deliveries?

If so, is it possible by Configuration? Please let me know.

Standard SAP will not allow loading after PGI.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    May 07, 2017 at 07:52 AM

    Hi Tom,

    May I know why you want to load after PGI , any reason ?

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Tom,

      I am unable to know what is the exact requirement but system will allow loading into TU after goods issue too.

      Step1: Create a delivery & Assign it to TU As below.

      Step2: Complete Picking + Do Goods Issue.

      So the system is throwing error so go to /SCWM/TU then do arrival at check point.

      Now go back to Delivery & Do the Goods Issue.

      Now Go to /SCWM/TU

      Perform Loading + Departure from check point.

      the only draw back is the outbound delivery loading status will not change.