Loading after PGI

Apr 17, 2017 at 10:50 AM

55

avatar image

Is it possible to carryout Loading onto a TU after Goods Issue has been posted for the assigned deliveries?

If so, is it possible by Configuration? Please let me know.

Standard SAP will not allow loading after PGI.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

VAMSIKRISHNA SRIRANGAM May 07, 2017 at 07:52 AM
0

Hi Tom,

May I know why you want to load after PGI , any reason ?

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Tom,

I am unable to know what is the exact requirement but system will allow loading into TU after goods issue too.

Step1: Create a delivery & Assign it to TU As below.

Step2: Complete Picking + Do Goods Issue.

So the system is throwing error so go to /SCWM/TU then do arrival at check point.

Now go back to Delivery & Do the Goods Issue.

Now Go to /SCWM/TU

Perform Loading + Departure from check point.

the only draw back is the outbound delivery loading status will not change.
1.jpg (121.7 kB)
2.jpg (139.4 kB)
3.jpg (247.4 kB)
4.jpg (14.3 kB)
4.jpg (14.3 kB)
5.jpg (81.7 kB)
6.jpg (37.7 kB)
7.jpg (37.8 kB)