Hi all

I'm working for a costumer right now, where we have implemented Plan Driven Procurement. We are running BBP_EXTREQ_TRANSFER in order to transfer the requisitions to SRM. The Costumer wants to control what requisitions that are transferred i.e. based on e.g. MRP controller, plant - but the program doesn't offer these variants.

Does anyone has any suggestions on how to solve this? Other than making a Z program ;o)