on 04-13-2017 12:58 PM
Hi Experts,
We are facing a problem as given below ;
We want to MRP based on the production plan for six month . Production plan has been given against plan version 01 for Six month ( Say , April - 6000 , May - 4000 , June - 10000, July - 11000, Aug- 12000 , September ) under MD61. Accordingly PIR has been generated for Six month . After that we have run MRP under MD02 / MD01 , during MRP execution , this is found that planned order generated against each first three month's production plan i.e April , May and June , But rest three months planned order not generated (i.e. July ,Aug,Sept) . Planning Horizon maintained 180 .
Please provide solution.
Regards,
Amit Biswas
Hi Amit,
There is a possibility to maintain the Planning Horizon, at Plant Level ( T code : OPPQ) (or) at the MRP Group Level( T code : OPPR)
Could you please check once, if any MRP Group is assigned for the Material. If assigned, what is the Planning Horizon maintained for the MRP Group ?
If not maintained, then system will consider the Plant level setting
Please take a look of the screen shot of the same
Kindly check & let me know, with your feedback/comments
Many Thanks for your quick feedback: Best Regards : Raja Sekhara Reddy Bannuru
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajasekahara ,
Sorry for delay in response ,
I have checked MPR group in material and this is correctly maintained . Also I have check OPPQ and OPPR both the cases planning Horizon in maintained as 300 .
Our problem , I have feed plan for six month any FERT material and after that , executed MRP , but after MRP execution planned order generated for 1st three month only and next three planned not generated .
Please help to resolve the issue.
Regards,
Amit Biswas
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.