Dear friends,

I have rum MRP in MD02 (Parameters as NETCH,3,2,1,2,1)

I converting my planned into production order. While carrying out scheduling for my order the system brings the order finish date as 2008 and start on 2006. It is really not practical. I have backward scheduling.

In my routing for that particular material i have maintained my std time per unit as 0.05min/unit. My order quantitty as 2000000. Why the system brings order finish date as 2008?

In my work center creation, under "capacity "tab i have entered distribution key as " SAP050". Is this key makes this scheduling like non practical.

If i set this distribution key, what actually the system will do?

please clarify

Thanks

Senthil