Message no:06117, not working in schedule agreement.

0 Kudos

My requirement is, For the partial qty if GR/IR done, then ssytem allowing to delete the SA line qty, which is not happened in PO.

Kindly suggest.

Accepted Solutions (0)

Answers (2)

Answers (2)

JL23
Active Contributor
0 Kudos

Can you show the schedule lines.

The IR matches with the GR, and if there are no open schedule lines for the SA item then it is allowed to delete it.

JL23
Active Contributor
0 Kudos

so it is like I already said: The IR matches with the GR, and if there are no open schedule lines for the SA item then it is allowed to delete it.

JL23
Active Contributor
0 Kudos

your question is not clear, I don't really get if your requirement is to get the error message or not get the error message.

There are quite many OSS notes addressing issues with having error message 06117

And only 1 OSS note is the opposite, that 06117 is not coming while it should be actually there (2031313)

0 Kudos

Hi, My concern is, in the case of PO,if the line item qty is 10, GR & IR done for 3 qty then we try to delete the line item system will give error as qty is less than the ordered qty, but in Schedule agreement if we run the scenario, then system allowing to delete , it is not throwing any error as like in PO.

Please suggest.

JL23
Active Contributor
0 Kudos

Do you delete the schedule agreement item or the delivery schedule?

Can you show screenshots?