Message no:06117, not working in schedule agreement.

My requirement is, For the partial qty if GR/IR done, then ssytem allowing to delete the SA line qty, which is not happened in PO.

Kindly suggest.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Apr 13, 2017 at 08:47 AM

    your question is not clear, I don't really get if your requirement is to get the error message or not get the error message.

    There are quite many OSS notes addressing issues with having error message 06117

    And only 1 OSS note is the opposite, that 06117 is not coming while it should be actually there (2031313)

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 13, 2017 at 09:42 AM

    Can you show the schedule lines.

    The IR matches with the GR, and if there are no open schedule lines for the SA item then it is allowed to delete it.