Assign source of supply is not working for Centrally agreed contracts

Hi,

I have already searched SCN extensively but couldn't find the answer.

We are trying to use Centrally agreed contracts. After creating Central contract (MK), while assigning source of supply to PR in ME57 the Central contracts doesn't appears, though Plant specific contracts & Info records does appears. Now, I can enter Central contract straight to PO, it works fine but we want to assign it by source of supply to PR as in our current process we are already assigning Plant specific contracts & Info records in source of supply(ME57) to PR and then convert PR to PO in ME21N.

Please suggest.

Regards

Amit

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 12, 2017 at 03:07 PM

    Make sure you use ALV as scope of list in ME57

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Jürgen,

      Yes, scope of list is ALV.

      In test client i created two new Vendors and two separate contracts for each of them(one Central contract & one Plant specific contract). Now in ME57 Source of supply, Central contract doesn't appears, only Plant specific contract appears.

      In forums, discussions are to create Contract release order(PO) for Central contracts but no suggestion on Source of supply assignment to PR in ME57.

      Thanks