on 04-12-2017 12:45 PM
Hi,
In case of Single Resource work center scenario, demand capacity will be distributed equally across all the days where demand is spanning.
The distribution is again within the demand time frame. Hence whenever a demand is falling in multiple days, spike in graph is observed at the end/begin of the day. Help document for the distribution of capacity can be found in 'Human Resource Capacity Scenario' section at
When demand falls outside the work center end time and if that is the weekend, capacity will be overloaded in the available time overlapping with the demand.
Please check if this is the case with you scenario.