Calculation graph calculation is wrong in single resource scenario.

  • Inconsistency with the graph when the availability is low. i.e, when the demand is more than availability the graph is showing high. Also the demand is changing, if we squeeze the graph or extend it.
  • Graph is not visible, When the operation ending on next day and there is no available of resource(Next day)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Apr 12, 2017 at 11:58 AM

    Hi,

    In case of Single Resource work center scenario, demand capacity will be distributed equally across all the days where demand is spanning.

    The distribution is again within the demand time frame. Hence whenever a demand is falling in multiple days, spike in graph is observed at the end/begin of the day. Help document for the distribution of capacity can be found in 'Human Resource Capacity Scenario' section at

    http://help-legacy.sap.com/saphelp_mrs900_erp/helpdata/en/d0/73435216033607e10000000a441470/content.htm

    When demand falls outside the work center end time and if that is the weekend, capacity will be overloaded in the available time overlapping with the demand.

    Please check if this is the case with you scenario.