ADJUSTEDTRANSPORT & ADJUSTEDTRANSPORTDS

Apr 11, 2017 at 07:17 PM

139

avatar image

Hi,

So in Supply Planning, the quantities coming from a vendor (location) to a DC (location) are represented by 2 Key Figures:

  • TRANSPORT (LOCLOCFR)
  • TRANSPORTDS (LOCLOCTO)

We can adjust these values with the following adjusted Key Figures:

  • ADJUSTEDTRANSPORT (LOCLOCFR)
  • ADJUSTEDTRANSPORTDS (LOCLOCTO)

Once you update 1 of the 4 KF and run the Supply Operator, all 4 KF will get the same values, but not necessarily in the same period if there is Lead Time between the locations.

Now my question : do I really need to wipe all 4 KF if I want to remove entries made in one of the 2 adjusted KF ? IF I change only the ADJUSTEDTRANSPORT and run the Operator, the values come back because it's still in ADJUSTEDTRANSPORTDS.

Have you guys found a easy process to clean these values (and I cannot use the parameter to reset adjusted values when I run the operator)?

*** Actually to update this post, if both set of KF are in the planning period of the operator, only the 2 Adjusted KF need to be wiped for the supply to revert to orignal values. However, if the Down Strean KF are in the past, and no value was set in them, removing the values in ADJUSTEDTRANSPORT is not enough for the TRANSPORT KF do be reverted back to it's original value.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Rohit Ranjan
Apr 13, 2017 at 06:54 AM
0

Hello Marc,

If a transport has already started in past and lies within the lead time, then it cannot be reset by updating value in ADJUSTEDTRANPORT key figure. Instead you need to initialize it using the parameter INITIALIZE_LEADTIME_HORIZON. See the detail in below SAP help link-

https://uacp2.hana.ondemand.com/viewer/feae3cea3cc549aaa9d9de7d363a83e6/1702/en-US/a5019e5641dff92ae10000000a4450e5.html

Thanks,

Rohit

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Hi,

I've read it again and again, I will test it. But from my understanding it would reset the transports in the leadtime horizon (in the past) and then plan in the future only ?

Thanks,

Marc

0

Hello Marc,

The parameter will will reset transport key figure which lies within lead time(could be some future time buckets as well). Outside the lead time horizon you should be able to reset using Adjusted transport key figure.

Thanks,

Rohit