MRP Run for STO

Apr 11, 2017 at 10:10 AM

103

avatar image
Former Member

Hi All,

In ME21N, we created a STO with document type 'UB' for 10 nos - Material Type-ROH.

PO contains information has Supplying Plant(1111) & Supplying Storage Location(DK01).

Supplying Plant(1111) has storage location (BH01) with 16 nos & storage location(DK01) with 4 nos.

We executed MRP Run in MD03 for Plant 1111 and expected that system will create a PR for shortage qty of 6 nos in storage location (DK01).

But system is considering plant stock during MRP run and not creating any PR's

I want to system to consider storage location stock.

Dinesh Kumar V.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

avatar image
Former Member Apr 13, 2017 at 06:01 AM
0

Normally, you can control the MRP run at storage location level with MRP areas or by excluding the storage location from the MRP run. In SAP online help (see Special Planning Processes) you can find detailed explanation for both solutions.

In a HANA system, you can use only the first option (MRP areas).