Skip to Content
0
Former Member
Nov 14, 2006 at 03:43 PM

SNP Interactive Planning- Production PLanned Key Figure

29 Views

In the detailed view of SNP interactive planning, component

product name is shown (It shows input product instead of the

output product) for Production Planned (Subcontract) key figure.

This happens only for the products displayed at subcontracting

locations (vendors). Though quantity planned is correctly

calculated and the right PPM as the source of supply is being

displayed without any error.

Plan at the Subcontracting Vendor

Mat# A is the Output product

Mat# b is the Input product

Mat # c is the Input product

A=b+c

Product A at subcontracting location in the SNP interactive

planning, when we look at the production planned key figure

details, the planned order has just one input component(b).

What we expect is either the Finished Part(A)or both the input

components(b,C)

Is there some kind of setting so that we can achieve the above?