Hi SAP Consultants,

Is there any Cost Center field in Production Order transaction CO01 ?

What are the tables where Production order data is stored/saved ?

Any help would be appreciated.

Thanks in advance.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 10, 2006 at 05:24 PM

    Hi

    I dont think there is Cost Centre filed in CO01, but it linked via worj centre which is used in routings. There is one table AUFK which is having cost centre, please check.

    Production Order tables

    AUFK Production order headers

    AFIH Maintenance order header

    AUFM Goods movement for prod. order

    AFKO Order header data PP orders

    AFPO Order item

    RESB Order componenten

    AFVC Order operations

    AFVV Quantities/dates/values in the operation

    AFVU User fields of the operation

    AFFL Work order sequence

    AFFH PRT assignment data for the work order(routing)

    AFRU Order completion confirmations

    Hope it helps

    regards

    Srinivas

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 14, 2006 at 09:12 PM

    Hi Parthivan,

    Production Order data is stored in following tables : AFKO , AUFK .

    AFKO - Order header data PP orders

    AUFK - Order master data

    In table AUFK you can find cost center field KOSTV ( from table CSKS ) .

    You can check the view ENT5233 - Production Order using SE11 .

    Let me know if you have any further questions on this.

    Please don't forget to reward points if this is helpful.

    Thanks.

    Ramesh Choragudi

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 15, 2019 at 08:58 AM

    Hi

    you can Use CO03 with Display overview and double click on Operation overview (or press F5) then double cklic on work center then you can see the cost center in field in costing tab.

    regards

    Farhad

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.