How to disable the Delivery Completed Indicator in Purchase order creation/change Screen ??

Currently our sap system allow user to set the Delivery Completed indicator in ME21N/ME22N .Now we want to disable this Delivery Completed in ME21N/ME22N Screen ?? Please explain any configuration level or enhancement available for the same ??

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Apr 10, 2017 at 08:10 AM

    How do you plan to set the complete indicator if you disabled the field?

    There might be rare cases where you have to close a PO which got only a partial delivery.

    You may realize this months later when it is no longer possible to cancel the receipt followed by a change of the PO quantity followed by a new receipt which would set the indicator automatically.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 10, 2017 at 07:45 AM

    Goto Purchase Order Field selection layout under SPRO - MM-> Purchasing -> Purchase Order - >Define Screen layout.

    Regards,

    Sagnik.

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 10, 2017 at 07:39 AM

    Hi,

    You can set the delivery completed indicator to display only mode

    spro-materials management-purchasing-purchase order-define screen layout at document level

    select document type and in GR-IR feild selection key , set Delivery completed indicator to display only mode.