cancel
Showing results for 
Search instead for 
Did you mean: 

PS - system status

Former Member
0 Kudos

hi all,

in PS is it possible to change system status from release mode to again created mode once you release the project.

if possible kindly be elaborate and provide the procedure.

regards,

dipankar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

You cannot change the status from Released to Created, as actual values from, for instance, purchase orders or confirmations may have been posted

Regards

Santosh

Former Member
0 Kudos

HI Santosh

Can we delete WBS Element which have cost but status has released .

Please confirm

Vikas Sharma

Bosch

former_member201206
Active Contributor
0 Kudos

The WBS can certainly be deleted, after the status is changed to Released. According the normal business process, the main chain status should be created, released, closed, then to be deletion. You may see the archiving captial for the project system for more information.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Wang

Please let me come to know that If WBS element have cost and status created , can we delete the WBS element .

2- If Top WBS element having status created and activity beneath this WBS element is released can we delete this WBS ?

Please help

Thanks

Former Member
0 Kudos

No SAP logically it isn't allowed to revert back from REL,