Different call horizons for each strategy package on same plan

Apr 08, 2017 at 02:24 PM

92

avatar image

Looking to set up plan and strategy to schedule as described below on a 3-package plan:

Strategy packages: 1-week, 24-weeks, 48-weeks

Call Dates:

1- Week, 7 day call ahead of plan date

24- Week, 21 day call ahead of plan date

48- Week, 28 days ahead of plan date

Both scenarios with or without hierarchy

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Peter Atkin Apr 11, 2017 at 11:40 AM
0

You can only have one Call Horizon on the plan..

If you need this by package, then you will need to develop a solution, possibly via:

  • User-exit IPRM0002
  • BADI BADI_EAM_EXIT_IPRM0002
  • BADI IPRM_MCP_UPD_CALLOBJ

.

PeteA

Show 1 Share
10 |10000 characters needed characters left characters exceeded

I'm facing the exact same Problem. Need to have seperatete call horizons by package.

With Exit IPRM0002 and BADI_EAM_EXIT_IPRM0002 I was only able to change the plandate. Aim is to change the Call date.

Looks like IPRM_MCP_UPD_CALLOBJ is only fired one time when IP10 is started. Parameters do not offer details of scheduled calls.

I saw in table T351P there is a field EROEF --> Call horizon in days (per maintenance package). I cant see that it is used somewhere.

Any other ideas?