Looking to set up plan and strategy to schedule as described below on a 3-package plan:

Strategy packages: 1-week, 24-weeks, 48-weeks

Call Dates:

1- Week, 7 day call ahead of plan date

24- Week, 21 day call ahead of plan date

48- Week, 28 days ahead of plan date

Both scenarios with or without hierarchy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 11, 2017 at 11:40 AM

    You can only have one Call Horizon on the plan..

    If you need this by package, then you will need to develop a solution, possibly via:

    • User-exit IPRM0002
    • BADI BADI_EAM_EXIT_IPRM0002
    • BADI IPRM_MCP_UPD_CALLOBJ

    .

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

    • I'm facing the exact same Problem. Need to have seperatete call horizons by package.

      With Exit IPRM0002 and BADI_EAM_EXIT_IPRM0002 I was only able to change the plandate. Aim is to change the Call date.

      Looks like IPRM_MCP_UPD_CALLOBJ is only fired one time when IP10 is started. Parameters do not offer details of scheduled calls.

      I saw in table T351P there is a field EROEF --> Call horizon in days (per maintenance package). I cant see that it is used somewhere.

      Any other ideas?