Dear all ,
I want to use ws20000075 workflow , but i am new to it , How do i go about . please send me if there are any documents pertaining to this work flow to raghavendra04@gmail.com
hi raghavendra,
WS20000075 is for PO Release if i am not wrong,
so first through SPRO configure your Release Strategy and Codes,
then go to SWETYPV or PFTC_CHG to activate your event by ticking the box 'Activate Linkage',
later in your WF Builder assign appropriate agents activate it and create a PO through ME21N,