I need to backflush material form 2 different storage locations on a Kanban basis for different components

Top level - Component 1 - LSRS, Component 2 - JLRS

Component 2 is part of a phantom subassembly item

I have changed everything at the BOM level but still cannot get it to work

I will happily send screen shots etc but I definitely need help please

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Did you change the production supply area on the work center?