on 11-06-2006 1:08 PM
Hi ,
I have created different release strategies .
Classification also done.
In release indicators (2 -which I selected), but now I want to change it into '4'.
So without deleting whole release strategies , it is possible to do the changes.
Then whether that release strategy accepts this changes.
Kindly advise.
regards,
Hi ,
You can change the Release indicator for the required release strategy . Not need to delete the existing.
But this change will be applicable only for new docuemts created.
Thanks & Regards,
sudhi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sandeep,
If u change the release indicator from 2 to 4, then it is changeable. It will be subjected to new release in the case of new strategy or value change.
You have to set the corresponding value in changeability indicator.
regards
Anand.C
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.