on 11-06-2006 5:59 AM
Hi, I am quite new to MM. I appreciate dearly if someone can help me here.
When we set PR release indicator changeability to 4 (Changeable, new release in case of new strat. or val. change), once PR is released, if there is any changes to qty or value, the PR will need to be released again.
How can i set it to, any changes in the PR (besides qty or value) also require new release? For example changing the material, plant or short text.
I tried to create new field selection key, but i am not sure how to configure it.
Hi.
I think you can use the changeability indicator 1 or 3. To activate this you should have two release strategy.
Hope this helps you.
Cheers
Umakanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
The Standard release stragtegy changeability indicators won't solve your requirment . changability indicator 4 resets the release only if 1) Value change 2) release strategy change due to your change in characterisitc value.
In your case of changing the plant , if it is going to change the release strategy then it resets the release ,otherwise the release strategy is not reset.
Hope it answers your question .Please reward points if u are satisfied with the answer.
Regards
Mani