on 04-06-2017 11:19 AM - last edited on 02-03-2024 10:27 PM by postmig_api_4
Hi,
We have a plan to upgrade existing BI platform(SAP BO 4. SP12) to SAP BO 4.1 SP8.
Before that we would like to sync UAT with Production,what is the best way to do sync between UAT and production..?
Thanks,
Brahma
Hi Brahma,
The best way to sync your UAT with production is Promotion Management.
Although you can also do backup and restore procedure.
1) Take a cold backup of your Production CMS database and File store. Restore it in your production CMS database and filestore.
2) Recreate a Server Intelligence Agent (SIA) and done do not start the SIA. Navigate to properties of SIA>> Configuration and change the "CLUSTER NAME".
3) Start the SIA.
Once done your UAT will become a replica of your production.
Please let me know in case of anything.
Regards,
AniketVN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Use promotion managemnet and move reports/universe/connections in UAT.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.