When using the Breakdown box on the notification, how do you report the time frame of the breakdown? Thanks in advance for your help.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Duraisamy Dhanaraj Apr 06, 2017 at 10:59 AM
0

Once we enable the breakdown check box, we need to enter malfunction start date and time

when we closing the notification, if we enter the malfunctiona end date and time , from these dates (Start and end date and time) system calculates the breakdown duration automatically.