Hell SAP Gurus

Pls clarify the following:

1. I have maintained release strategy for PR & PO

with clasification. Green light is showing for the strategy which i have maintained. In which i have selected

plant , material group, purch. org, doc type & Pur.group.

(1000, 004, 1000, nb, 000).

When am raising Requisition Or Purchase Order system says

this item /pr not covered under release strategy. Could u pls explain me where i have gone wrong?

2. When am using MIGO while posting system showig warning msg: period 010 and 2006 not open. for which i tried MMPI

for initialization , which is also giving error msg like

follow Note: 786387 initialization proceedure. Pls give me solution for this.