Can SAP create a new MvT between 103 and 105 ?.

Can SAP create a new MvT between 103 and 105 ?.

Because we receiving items in Abudhabi Transit Store with movement 103,and then we send items to our store in another place in das Island, we want to track items before GRN T 105, is it possible to create new MVT before 105 ?.
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Apr 05, 2017 at 04:00 PM

    GR blocked stock can only be received with 105 or cancelled with 104

    there is nothing else that can be done between 103 and 105.