cancel
Showing results for 
Search instead for 
Did you mean: 

MRP Purchase Requisition.

Former Member
0 Kudos

MRP-Purchase Requisition

Project--WBS ElementNetworkActivityMaterial--Reservation.

MRP Run (MD01) -


Planned Orders created-----Collective conversion of planned orders into Purchase Requisitions (MD15).

Purchase Requisition is created for quantity (10 Nos.) against the Reservation for the Project. Suppose if we change the quantity in Reservation (5 Nos.), we need to update the same Purchase Requisition for the Quantity (5 Nos.) during the Next MRP Run.

When the Material Requirement date is in Future, during the MRP Run the Purchase Requisition is creating again and again by deleting the Previous Purchase Requisition.

If any changes made in the Project Reservation, are these changes can automatically updated in the same Purchase Requisition in the next MRP Run?

At present during next MRP Run the system creating new Purchase Requisition by deleting the Previous Purchase Requisition.

Now the issue is we need the changes to be updated in the same Purchase Requisition.

Can any body tell how to solve the above issue?

Accepted Solutions (0)

Answers (3)

Answers (3)

fabio_almeida
Active Participant
0 Kudos

It should be already resolved.

Closing old thread.

Former Member
0 Kudos

Hi Ravi,

In your first post you want the system to update the existing PR.

->This can be done, as long as you do not firmed your PR, and the planning mode is 1

In your second post you want the system to delete the existing PR and create new PR according to new requirement, at the same time the existing PR already firmed.

-> Since your PR is already firmed, it will not changed automatically.

Former Member
0 Kudos

Hi Ravi,

In MD01, ensure that the Planning Mode is 1(Adapt planning data (normal mode)) instead of 3(Delete and recreate planning data).

Rgds,

Ong

Former Member
0 Kudos

Hi Ong,

MRP-Purchase Requisition

Project--WBS ElementNetworkActivityMaterial--Reservation.

MRP Run (MD01) -


Planned Orders created-----Collective conversion of planned orders into Purchase Requisitions (MD15).

We are using the planning mode as 1 as you are suggested.

Purchase Requisition is created for quantity (10 Nos.) against the Reservation for the Project. We are firming this Purchase Requisition so that it will not create another Purchase Requisition by deleting previous Purchase Requisition in the next Planning run.

If any changes made in the Project Reservation (say quantity from 10 Nos. to 5 Nos.) in the next MRP Run we need to create the New Purchase Requisition for the quantity for 5 Nos. and by deleting the previous Purchase Requisition having the quantity 10 Nos.

Can you help me in this scenario to solve the above issue?

Message was edited by: Ravi Raju Muddaluru