hi friends can any body sent me docs for ASAP methodology and docs on Blue Prints and if possible bw 2001 interview questions to my mail id cforfriend@yahoo.com thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Oct 25, 2006 at 04:03 AM

    Hi ,

    The BW Project guidelines can be as follows ,

    Stages in BW project

    1 Project Preparation / Requirement Gathering

    2 Business Blueprint

    3 Realization

    4 Final Preparation

    5 GO Live & Support

    Project Preparation / Requirement Gathering

    Collect requirement thru interviews with Business teams /Core users / Information Leaders .

    Study & analyze KPI 's (key figures) of Business process .

    Identify the measurement criteria's (Characteristics).

    Understand the Drill down requirements if any.

    Understand the Business process data flow if any .

    Identify the needs for data staging layers in BW – (i.e need for ODS if any)

    Understand the system landscape .

    Prepare Final Requirements Documents in the form of Functional Specifications containing :

    Report Owners,

    Data flow ,

    KPI’s ,

    measurement criteria’s,

    Report format along with drilldown requirements .

    -


    2 Business Blueprint

    Check Business content against the requirements

    Check for appropriate

    Info Objects - Key figures & Characters

    Check for Info cubes / ODS

    Check for data sources & identify fields in source system

    Identify Master data

    document all the information in a file – follow standard templates

    Prepare final solution

    Identify differences (Gaps) between Business Content & Functional

    specification. propose new solutions/Developments & changes if required at different levels such as Info Objects ,Info cube , Data source etc . Document the gaps & respective solutions proposed– follow standard templates

    Design & Documentation

    Design the ERD & MDM diagrams for each cube & related objects

    Design the primary keys/data fields for intermediate Storage in ODS

    Design the Data flow charts right from data source up to Cube .

    Consider the performance parameters while designing data models

    Prepare High level / Low level design documents for each data model.--- follow standard templates

    Identify the Roles & Authorizations required and Document it – follow standard templates

    final review of design with core BW users .

    Sign off the BBP documents

    -


    3 Realization

    Check & Apply Latest Patches/Packages ...in BW & R/3 systems.

    Activate/Build & enhance the cubes/ODS as per data model designs...maintain the version documents .

    Identify & activate Info objects / Master data info sources / attributes ,prepare update rules

    Assign data sources .prepare transfer rules , prepare multi providers . prepare Info packages .

    perform the unit testing for data loads….both for master data & transaction data .

    develop & test the end user queries .

    Design the process chains ,schedule & test

    create authorizations / Roles …assign to users ..and test

    Apply necessary patches & Notes if any .

    freeze & release the final objects to quality systems

    perform quality tests .

    Re design if required . (document changes, maintain versions)

    -


    4 Final Preparation

    Prepare the final check list of objects to be released .identify the dependencies & sequence of release

    perform Go Live checks as recommended by SAP in production system

    keep up to date Patch Levels in Production system

    Test for production scenarios in a pre-production system which is a replica of production system .

    Do not Encourage the changes at this stage .

    freeze the objects .

    -


    5 GO Live & Support

    keep up to date Patch Levels

    Release the objects to production system

    Run the set ups in R/3 source system & Initialize Loads in BW

    Schedule Batch jobs in R/3 system (Delta loads)

    schedule the process chains in BW .

    Performance tuning – on going activity

    Enhancements - if any

    You can get some detailed information in the following link.

    http://sap.ittoolbox.com/documents/document.asp?i=3581

    Try to go to ASAP implementation roadmap.

    https://websmp103.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000420636&_SCENARIO=01100035870000000202

    Check the links below that gives you brief overview of the above steps .

    https://websmp201.sap-ag.de/asap

    http://www.geocities.com/santosh_karkhanis/ASAP/

    -


    https://websmp201.sap-ag.de/asap

    http://www.geocities.com/santosh_karkhanis/ASAP/

    https://service.sap.com/roadmaps

    https://websmp104.sap-ag.de/bi

    ***Please reward if useful.**

    Blue Print:

    http://www.sap.com/services/servsuptech/bestpractices/index.epx --- look for blueprint

    http://iris.tennessee.edu/Blueprint/BW/BW-Blue%20Print-Final.doc

    http://help.sap.com/bp_biv335/BI_EN/html/Business_Blueprint.htm

    You can get some detailed information in the following link.

    http://sap.ittoolbox.com/documents/document.asp?i=3581

    Hope these links helps you.

    Regards

    CSM Reddy

    Message was edited by: REDDY CSM

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Oct 25, 2006 at 12:35 PM

    helo reddy thanks for u r reply but all links which you sent are asking login id pwd

    do you have that any way i assigned pointe and thanks alot for your info

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.