cancel
Showing results for 
Search instead for 
Did you mean: 

Editable in Current or Future - Technical Weeks vs Calendar Weeks

marc_laberge
Participant
0 Kudos

Hi,

I understand that this is standard behavior, according to this note:

2438953 - IBP: Cannot edit Key Figure in current time buckets

If I open a planning view in Months on a weekly KF that is set as "Editable in Current or Future", I will not be able to change value in the current month, because it has already started.

However, if we do this exercise on Technical Weeks vs Calendar Weeks, it's a bit annoying.

We use Technical weeks only to be able to aggregate to Calendar Months, but we plan all in Calendar Weeks, so users will see data in Calendar Weeks. So for current Week 14, I cannot change any Key Figure in current Calendar Weeks and users would have to go down to TWeek 14 to be able to change the values.

This is a bit annoying, since it's 1 for 1 and I'm planning in Weeks. Is there a way to go around this limitation ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Marc,

As a workaround you can do following

1) Make your specific keyfigure "All Editable". This will allow user to edit the data in current week or month.

2) Create a new template with planning start date as current bucket ( week or month)

3) Assign template to relevant users

Regards,

Hemant

Answers (3)

Answers (3)

mkorndoerfer
Contributor
0 Kudos

Hello Marc,

I do not believe there is any other way to go around this besides Hemant Gupta's suggestion. Even an enhancement request could be hard to achieve as this behavior includes technical reasons for working this way.

Still, if you think this functionality would be a business enhancement for futures releases, please feel free to suggest it as an enhancement request on Influence channel: 11 or also by Customer Connection program email address: customer-connection@sap.com.

Best regards,
Matheus

marc_laberge
Participant
0 Kudos

Well, thanks for confirming the standard behavior. However, this is not ideal, I'm wondering if there is ways I could go around this issue ?

lingaiahvanam
Active Contributor
0 Kudos

Hi,

User can not change key figure at calendar week (14) if your planning level root selected as week(technical).

or

In time profile week base level is week(technical). So user can not change value at calendar week.

Best Regards,

Lingaiah