Service level % in MRP2 view

hi gurus !!!

If we change the value of Service level(%) in MRP2 view of the material does it have any effect during the MRP run ?

If yes then pls specify ?

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Oct 20, 2006 at 08:23 PM

    Hi Kaushik

    Definately it is going to affect the MRP.

    As it is going to increase the SAfty stock for the same item

    For details refer bellow.

    Service level

    Percentage specifying what proportion of the requirement is to be covered by the warehouse stock.

    Use

    The system uses the service level to calculate the safety stock.

    The higher the service level, the higher will be the safety stock calculated by the system to compensate for additional consumption or delays in delivery.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.