on 10-20-2006 12:54 PM
hi gurus !!!
If we change the value of Service level(%) in MRP2 view of the material does it have any effect during the MRP run ?
If yes then pls specify ?
Hi Kaushik
Definately it is going to affect the MRP.
As it is going to increase the SAfty stock for the same item
For details refer bellow.
Service level
Percentage specifying what proportion of the requirement is to be covered by the warehouse stock.
Use
The system uses the service level to calculate the safety stock.
The higher the service level, the higher will be the safety stock calculated by the system to compensate for additional consumption or delays in delivery.